Pre-cast pile driving for the above project is at the final stage. This project consists of supply and driving 103 number of pile point with the 300x300mm, 355x355mm and 400x400mm pile sizes. To the date, 96 number of pile points have completed (about 93%). Our project period is 3months and its due date is 2nd October 2018.
Garbage Dump site at Karadiyana
2018
Waste Management Authority (Western Province)
September 19, 2018
Ongoing, Precast Piling