Pre-cast pile driving work at Karadiyana

The progress of the pre-cast pile driving work for the construction of proposed mihisaru resource management training centre at Karadiyana is at its final stage. This project consists of the supply and driving of 103 precast square piles of dimensions 300x300mm, 355x355mm, and 400x400mm, and lengths (9m+6m) and (8m+6m). So far we have driven 93 precast piles, which is equal to 1264LM of 1350LM (assumed) to date, bring the project to a 94% completion. Our project period is 3 months and its due date is 2nd October 2018. Our target is to complete all the driving works by the 27th of September.